equivalent units
Imagine a department finishes 800 toys completely this month, but also has 400 toys still on the line that are only half done. How much work did the department really do? Not 1,200 toys' worth, because the half-done ones aren't finished — but not just 800 either, because real effort and material went into those 400. The honest answer: 800 finished plus the equivalent of 200 more (400 toys at 50 percent). The department did 1,000 toys' worth of work. That 'work expressed as whole finished units' is the idea of equivalent units.
Equivalent units convert partially completed work into the number of fully completed units it equals, so that costs can be averaged sensibly in process costing. Crucially, completion is usually tracked separately for materials and for conversion (labor plus overhead), because a unit can be 100 percent complete as to materials (all the plastic added at the start) but only 40 percent complete as to conversion (still being assembled). So a process cost report typically shows two equivalent-unit columns. You compute equivalent units for ending work in process, add the units completed and transferred out, and that total becomes the denominator when figuring cost per equivalent unit.
Equivalent units matter because without them, dividing total cost by a raw headcount of units would either overstate or understate unit cost whenever inventory is partly finished — which it almost always is. They sit at the heart of every process-costing calculation and differ between the weighted-average and FIFO methods in how they treat the work already done last period on beginning inventory. A frequent error is applying a single completion percentage to materials and conversion together; in practice these two almost always have different completion stages and must be handled in separate columns.
Ending work in process: 400 units, 100 percent complete for materials, 25 percent complete for conversion. Equivalent units this represents = 400 for materials but only 100 for conversion (400 x 0.25). The two figures are added to completed units in their own columns.
Materials and conversion usually have different completion percentages.
Units completed and transferred out are always 100 percent complete; the completion percentage only matters for units still in ending work in process.